CRIXÁS PERMITTING ADVANCES
TOWARDS FINAL REVIEW
HIGHLIGHTS
• Engagement with the competent state environmental authority,
(State Secretariat of Environment and Sustainable Development
or “SEMAD”, has remained ongoing in relation to the re-issue of
the environmental permit for the Crixás Gold Tailings Project.
• Raiden, together with the vendor’s legal and engineering teams,
has now addressed all administrative, legal and technical
items requested by SEMAD.
• A water management report has been completed and is being
prepared for submission to SEMAD in the coming days. This
report represents the last outstanding item requested by
SEMAD under the current review process and is expected to
support final regulatory review.
• Subject to the re-issue of the environmental permit and its
verification by the SEMAD, Raiden aims to rapidly evaluate the
Project’s near-term production potential.A
• Raiden’s evaluation workstreams will consist of:
1. Execution of an initial drilling program of sufficient scale to
support a JORC-compliant Mineral Resource Estimate;
2. Fast-tracked metallurgical evaluation to define the preferred
processing route, with a focus on simple gravity and
potentially flotation routes; and
3. Progressing to a Final Investment Decision (FID) subject to findings from the
above workstreams.
• The above evaluation process is estimated to cost <A$1 million. This cost estimate is
preliminary and subject to change.
• Subject to the results of the evaluation process and FID, Crixás has the potential to
provide Raiden with near-term and low-cost pathway to gold production.A
• In parallel, Raiden has continued to review potential acquisition opportunities that it
considers have strong potential to be value-accretive on a per-share basis, in line with
its ongoing Corporate Strategy.1
Engage directly with us by commenting on our latest announcements via InvestorHub.
You can view and comment on this announcement here.
ASX CODE: RDN
DAX CODE: YM4
BOARD &
MANAGEMENT
Non-Executive
Chairman
Mr Michael Davy
Managing Director
Mr Dusko Ljubojevic
Non-Executive Director
& Company Secretary
Ms Kyla Garic
ASSET PORTFOLIO
AUSTRALIA
Li, Au, Cu, Ni & PGE
BULGARIA
Cu, Au & Ag
ASX RELEASE | 15 June 2026
Page 2 of 7
Raiden Resources Limited (ASX: RDN) (“Raiden” or “the Company”) is pleased to
provide an update on the Crixás Tailings Gold Project (“Crixás” or “the Project”) in Goiás
State, Brazil.
Mr Dusko Ljubojevic, Managing Director of Raiden commented:
“We are now entering the final phases of the approval process for Crixás. Strategically for
Raiden, our goal is to rapidly evaluate and, if feasible, advance a fast-tracked production
route for the Project.
To this end, in collaboration with the Project vendor and independent environmental
contractors, we have progressed the relevant permitting workstreams with SEMAD. All
administrative, legal and technical items requested under the current review process have
now been addressed, with the water management report now completed and being
prepared for submission.
Once all necessary approvals have been received, Raiden intends to rapidly undertake its
planned evaluation process for the Project, including drilling and metallurgical programs.
These workstreams are intended to support the delivery of a JORC resource and determining
the ideal processing route. We continue to view Crixás as a compelling opportunity reach a
near-term production outcome, given the Project’s access to infrastructure, power, and
services, together with the inherent advantages of a tailings reprocessing opportunity.
Importantly, in parallel with our ongoing work at Crixás, Raiden is continuing to review new
potential acquisitions that align with our corporate strategy and that we believe have
meaningful scope to generate value for shareholders. I look forward to reporting on further
progress as appropriate in due course.”
OVERVIEW
As previously announced,2
Raiden has secured the right to acquire an 85% commercial
interest in the Crixás Gold Tailings Project in Brazil, located ~5kms from the town of Crixás
and ~450 kms north-west of Brasília, the capital of Brazil (Figure 1). The Project
encompasses an area of 28.79 hectares and comprises a large, valley-fill gold tailings
deposit derived from decades of intensive artisanal mining. Of note, is the fact that the
A
Cautionary Statement
The Crixás Tailings Gold Project does not currently contain any Mineral Resource or Ore Reserve estimates reported in
accordance with the JORC Code (2012). References to historical mining, sampling, production and tailings characteristics are
based on historical and vendor-supplied information, including a technical report completed in 2010 by GéoExpl’Au
International, which was not prepared in accordance with the JORC Code and has not been independently verified by Raiden.
These data are considered conceptual and should not be relied upon as indications of grade, tonnage or economic viability.
Any reference to the potential for gold resources, production, capital-efficiency and other geological or commercial
information is conceptual in nature and remains subject to further work. Further work includes and is not limited to
confirmatory drilling and sampling, metallurgical testwork, resource estimation, engineering studies and the receipt of all
required regulatory approvals.
ASX RELEASE | 15 June 2026
Page 3 of 7
tailings have not been processed by any modern technologies (including milling), but by
stamp mills, which do not achieve the recoveries of gold as modern processing plants.
Furthermore, taking into account that the original ore was high grade, management
believe that economic grades of gold remain and may be recoverable through relatively
simple processes.
Given the presence of existing on-site infrastructure, access to water and nearby grid
power, and historical work indicating significant volumes of unrecovered gold-bearing
material, Raiden considers the Crixás Project to have potential to support a near-
term, low-CAPEX production scenario.2,A
Raiden’s current focus is to finalise the
remaining administrative, regulatory and project preparation workstreams to support
project advancement and ultimately a Final Investment Decision (FID) for development.
Figure 1: Project Location Map
REGULATORY AND PERMITTING PROGRESS
The vendors of the Crixás project have progressed the technical, environmental and
regulatory workstreams required to support the Project’s advancement towards
ASX RELEASE | 15 June 2026
Page 4 of 7
development and production. This work has built on the ongoing progress at the Project
as detailed in the Company’s previous ASX update on Crixás.3
Engagement with SEMAD, the competent state environmental authority, has remained
ongoing as part of the environmental permit re-issue process. Management, together
with the vendor’s legal and engineering teams, have addressed all of the administrative,
legal and technical reporting items requested by SEMAD under the current review
process.
The last outstanding item under the current SEMAD requests related to the preparation
of a water management plan. This required the determination of relevant water flow rates
for the creek, which traverses the Project area and the design of a water management
plan for the project area. This work has now been completed and the final report has been
prepared.
The final report, which is intended to address the current queries raised by SEMAD, is
expected to be submitted to SEMAD in the coming days for review. Subject to SEMAD’s
review and any further regulatory requirements, the Company is targeting the re-issue of
the environmental permit for the Crixás Gold Tailings Project.
The re-issue of the environmental permit, together with any required verification or
approval by the Brazilian Mining Authority, remains the key regulatory step required
before the Company can commence its planned evaluation activities at Crixás, including
drilling and metallurgical testwork.
OPERATIONAL READINESS WORKSTREAMS
In parallel with permitting and regulatory activities, Raiden has progressed a range of
operational workstreams to support rapid project advancement, subject to approvals.
Drilling contractors and technical teams have been identified and remain available to
commence work following receipt of the required approvals. The Company’s planned
initial work program remains focused on a drilling program aimed at delivering a JORC-
compliant Mineral Resource Estimate.
In parallel, Raiden intends to fast-track metallurgical evaluation to define an appropriate
processing route, with a focus on simple gravity and potentially flotation recoveries. These
workstreams are intended to provide the technical basis for Raiden to complete a study
of the viability of the Project and progress towards a Final Investment Decision.
ENVISAGED PRODUCTION PATHWAY
The strategic benefit of the Crixás Gold Tailings Project remains its potential to reach a
fast-tracked and capital-light production scenario.2,A
To this end, Raiden has commenced
ASX RELEASE | 15 June 2026
Page 5 of 7
preliminary engagement with processing plant commissioning teams to ensure that,
subject to FID, the Company is positioned to rapidly execute its development program.
NEXT STEPS FOLLOWING APPROVALS
Following the receipt of the necessary approvals, Raiden intends to rapidly undertake
evaluation and development workstreams. This includes the execution of a drilling
program aimed at delivering a JORC-compliant Mineral Resource Estimate (MRE). In
parallel, Raiden will fast-track metallurgical evaluation to define an appropriate processing
route, with a focus on simple gravity and potentially flotation recoveries.
Subject to the outcomes of the above resource drilling and metallurgical workstreams,
the Company aims to progress to FID as soon as practicable.
As previously announced,2
Raiden notes that tailings reprocessing projects typically
benefit from pre-stripped, free-digging material, low mining costs and relatively
simple gravity-dominant processing flowsheets. When combined with the existing
infrastructure at site and the Project’s access to power, labour and services, Raiden
believes Crixás has the potential to support a modest-scale operation with a shorter
development lead time (compared to a conventional greenfield hard-rock project).2,A
The Company will continue to update shareholders on material developments at Crixás in
accordance with its continuous disclosure obligations.
This ASX announcement has been authorised for release by the Board of Raiden Resources
Limited.
A
Cautionary Statement
The Crixás Tailings Gold Project does not currently contain any Mineral Resource or Ore Reserve estimates reported in
accordance with the JORC Code (2012). References to historical mining, sampling, production and tailings characteristics are
based on historical and vendor-supplied information, including a technical report completed in 2010 by GéoExpl’Au
International, which was not prepared in accordance with the JORC Code and has not been independently verified by Raiden.
These data are considered conceptual and should not be relied upon as indications of grade, tonnage or economic viability.
Any reference to the potential for gold resources, production, capital-efficiency and other geological or commercial
information is conceptual in nature and remains subject to further work. Further work includes and is not limited to
confirmatory drilling and sampling, metallurgical testwork, resource estimation, engineering studies and the receipt of all
required regulatory approvals.
ASX RELEASE | 15 June 2026
Page 6 of 7
We value your feedback and questions.
Engage directly with us by commenting on our latest announcements via InvestorHub.
You can view and comment on this announcement here.
FOR FURTHER INFORMATION PLEASE CONTACT
DUSKO LJUBOJEVIC
Managing Director
RAIDEN RESOURCES LIMITED
info@raidenresources.com.au
www.raidenresources.com.au
ASX Announcements referenced to directly, or in the commentary of, this ASX release
1
ASX:RDN Strategy update - Positioning for Value and Growth, 14 April 2025
2
ASX:RDN Significant Gold Tailings Reprocessing Opportunity Secured, 20 November 2025
3
ASX:RDN Crixas Gold Tailings Project Due Diligence & Progress Update, 15 April 2026
Competent Person's and Compliance Statement
The information in the referenced announcements 2-3 footnoted above that relate to Exploration Results
have previously been released to the ASX. The Company confirms that it is not aware of any information or
data that materially affects the information included in the market announcements, and that all material
assumptions and technical parameters underpinning the announcements continue to apply. The Company
confirms that the form and context in which the Competent Person’s findings are presented have not been
materially modified from the original market announcements.
Disclaimer:
Forward-looking statements are statements that are not historical facts. Words such as “expect(s)”, “feel(s)”,
“believe(s)”, “will”, “may”, “anticipate(s)”, “potential(s)”and similar expressions are intended to identify
forward-looking statements. These statements include, but are not limited to statements regarding future
production, resources or reserves and exploration results. All of such statements are subject to certain risks
and uncertainties, many of which are difficult to predict and generally beyond the control of the Company,
that could cause actual results to differ materially from those expressed in, or implied or projected by, the
forward-looking information and statements. These risks and uncertainties include, but are not limited to:
(i) those relating to the interpretation of drill results, the geology, grade and continuity of mineral deposits
and conclusions of economic evaluations, (ii) risks relating to possible variations in reserves, grade, planned
mining dilution and ore loss, or recovery rates and changes in project parameters as plans continue to be
refined, (iii) the potential for delays in exploration or development activities or the completion of feasibility
studies, (iv) risks related to commodity price and foreign exchange rate fluctuations, (v) risks related to
failure to obtain adequate financing on a timely basis and on acceptable terms or delays in obtaining
governmental approvals or in the completion of development or construction activities, and (vi) other risks
and uncertainties related to the Company’s prospects, properties and business strategy. Investors are
ASX RELEASE | 15 June 2026
Page 7 of 7
cautioned not to place undue reliance on these forward-looking statements that speak only as of the date
hereof, and the Company does not undertake any obligation to revise and disseminate forward-looking
statements to reflect events or circumstances after the date hereof, or to reflect the occurrence of or non-
occurrence of any events.
About Raiden Resources
Raiden Resources Limited (ASX:RDN / DAX:YM4) is a dual listed base metal & gold exploration Company
focused on identifying and discovering significant and economically attractive mineral deposits. Driven by
a passion for unlocking discoveries that create shareholder value and the support of a strong corporate
treasury, Raiden is committed to achieving exploration success.
The Company’s portfolio of projects includes the Andover South lithium project. The Company also holds
the rights to the advanced Mt Sholl nickel-copper-cobalt-PGE and the Arrow gold projects in the Pilbara
region of Western Australia. In addition, the Company holds the rights to multiple projects in the emerging
and prolific Western Tethyan metallogenic belt in Eastern Europe, where it has established a significant
exploration footprint in Bulgaria.