Quarterly Activities/Appendix 5B Cash Flow Report
Released
Released
Announcement PDF
ASX RELEASE | 15 April 2024
RAIDEN QUARTERLY ACTIVITIES REPORT
FOR PERIOD ENDED 31 MARCH 2024
Highlights
ASX CODE: RDN
• Andover South Project
DAX CODE: YM4
•
The Company secured a archaeological/anthropological
heritage survey for the Andover South Lithium Project1
BOARD &
MANAGEMENT
•
Heritage survey scheduled to commence last week of March
‘24
Non-Executive
Chairman
Mr Michael Davy
• Andover North Project
•
The Company secured a archaeological/anthropological
heritage survey for the Andover North Lithium Project2
•
Survey scheduled to commence following the Andover South
heritage survey
Managing Director
Mr Dusko Ljubojevic
Non-Executive Director
Mr Dale Ginn
Non-Executive Director
& Company Secretary
Ms Kyla Garic
• Mt Sholl Ni-Cu Project
•
Infill soil sampling program defined a new, high-grade nickel
target on the Mt Sholl project3
•
IP Survey over main deposit demonstrates significant upside for
further Ni-Cu sulphide mineralisation at depth4
• Mt Sholl Li Project
•
Infill soil sampling results have confirmed and refined multiple
Lithium in soil anomalies on the Mt Sholl Project5
Chief Operating Officer
Mr Warrick Clent
ASSET PORTFOLIO
SERBIA
Cu & Au
BULGARIA
Cu, Au & Ag
AUSTRALIA
Li, Au, Cu, Ni & PGE
Raiden Resources Limited (ASX: RDN) (“Raiden” or “the
Company”) is pleased to provide its report on activities and progress
made during the March 2024 Quarter:
Page 1 of 16
P 08 6158 9990 F 08 6268 4926
Suite 7, 63 Shepperton Road, Victoria Park, 6100
Australia
ASX RELEASE | 15 April 2024
Exploration Activities in Western Australia
Andover Project (South and North)
During the quarter the Company secured the archaeological/anthropological heritage
survey (“heritage surveys”), with the Ngarluma Aboriginal Corporation (“NAC”) over the
Andover South Lithium Project and the Andover North Lithium Project. The Company is
pleased to proactively engage with the Ngarluma Traditional Owners across the project
area, the Company’s objective is to ensure the Traditional Owners knowledge of the area
is utilised to avoid areas of cultural significance
The Andover South Heritage Survey commenced on the 25 March 2024 and were over the
Company’s priority lithium-bearing pegmatite targets at the Andover South Project area
comprising tenements (E47/4061 & E47/4062). The heritage survey encompasses areas
where Raiden has defined priority targets for drilling over the high-grade lithium-bearing
pegmatites at Andover South6. The Heritage Survey on the Andover North Lithium Project
comprising tenements (E47/3849, P47/2028, E47/4063 & E47/4603) commenced in early
April.
It is the Company’s objective to commence with drilling activities, across the entire project
area as soon as possible after both the heritage surveys have been concluded and all
regulatory processes for the grant of tenement E47/4062 have been completed.
Page 2 of 16
ASX RELEASE | 15 April 2024
Figure 1: Raiden’s Andover North and South Project and adjacent Azure Minerals Ltd.’s Andover
Lithium project7,8
Mt Sholl Project
Mt Sholl Ni-Cu Project
During the reporting period the Company reported on the results of a work program,
which included infill soil sampling over the northern parts of the Mt Sholl project area.
The sampling results defined a high-grade nickel in soil anomaly3, extending over several
kilometres along a WNW striking corridor. The peak value defined was 1,770ppm Ni with
multiple anomalies, constrained by >900ppm Ni values, extending across the northern
parts of the project area. All the sampling and analysis was carried out under the
memorandum of understanding (“MOU”)10 with First Quantum Minerals, with First
Quantum sole funding all the base metal related activities on the Mt Sholl project.
The source of the nickel anomalies is not known, but may be related to a potential
Volcanogenic Massive Sulphide (“VMS”) system. These anomalies add further district
scale potential to Raiden’s base metal portfolio in the Pilbara.
Further field mapping and potential geophysical surveys are being undertaken by First
Quantum over the nickel anomalies defined by this soil program.
Page 3 of 16
ASX RELEASE | 15 April 2024
Figure 2: Mt Sholl project with Nickel soil sampling results3
As announced9, First Quantum Minerals funded and completed the geophysical Induced
Polarisation (“IP”) survey over the northern extent of the Mt Sholl B2 Ni-Cu-PGE deposit
utilising a gradient array method and then following up on the defined anomalous zone
with two dipole-dipole sections. The aim of the IP survey was to trial the method over
the known mineralisation to define the potential response within the disseminated style
of mineralisation.
The results from the initial 3.8km2 gradient array grid survey outlined a 1,000m x 200m
chargeability anomaly which is offset to the east of the currently drill defined B2 NiCu-PGE mineral resource area (Figure 3). This chargeability response is hypothesised to
define a potential zone of disseminated mineralisation, but drill testing will be required
to prove this in the future.
Page 4 of 16
ASX RELEASE | 15 April 2024
Figure 3: B2 Deposit IP Survey Area - Gradient Array chargeability anomaly with historic
drilling9
Following on from the definition of this anomalous zone, First Quantum used the dipole
-dipole IP survey method across two sections, Line_2000N & Line_2950N, to further
define the chargeability response.
These two follow up dipole-dipole IP sections have defined chargeability responses that
appear to correlate well with the interpreted SW plunge of the B2 mineralisation. The
southern dipole-dipole section identified an anomalously chargeable feature located
within 150m of the surface (Figure 4).
Following on from the definition of this anomalous zone, First Quantum used the dipole
-dipole IP survey method across two sections, Line_2000N & Line_2950N, to further
define the chargeability response.
These two follow up dipole-dipole IP sections have defined chargeability responses that
appear to correlate well with the interpreted SW plunge of the B2 mineralisation. The
Page 5 of 16
ASX RELEASE | 15 April 2024
southern dipole-dipole section identified an anomalously chargeable feature located
within 150m of the surface (Figure 4).
Figure 4: B2 Deposit IP Survey Area – Dipole-dipole stacked sections with historic drilling and
reported mineralisation shells9 in an isometric view orientated North
It should be noted that while there is historical drilling collared over the northern part of
this chargeability, it was all terminated at very shallow depths and has not tested the
shallowly plunging chargeability anomaly.
Likewise in the southern zone of the chargeability anomaly no drilling has tested this
new target area.
First Quantum have planned further work over the Mt Sholl Ni-Cu-PGE deposits
inclusive of a ground electromagnetic (“EM”) survey. The objective of the EM survey is
to define further potential zones of massive sulphide mineralisation, which are known to
be hosted within the lower tenor disseminated mineralisation zones on the Mt Sholl
deposits.
Page 6 of 16
ASX RELEASE | 15 April 2024
Mt Sholl Lithium Project
During the quarter the Company announced the results of an infill soil sampling program5,
designed to follow up and define in further detail previously identified anomalies
generated during the 202312 sampling campaign. The infill sampling grids were executed
on a 50 metre by 100 metre grid and a 50 metre by 200 metre grid over the anomalies,
infilling the original survey line spacing.
As a result, the lithium anomalies are currently further constrained within distinct
geometries, with peak values of up to 188 ppm Li (405 ppm Li2O) in soils. The geometry
of the defined anomalies appears to broadly reflect the geometry of the mapped
pegmatites in the south-east zone of the tenement, and the pegmatite trends on
GreenTech’s (ASX: GRE) Osbourne project12 to the east of the Mt Sholl project. To obtain
further information additional mapping and evaluation of these trends is being
considered as next steps with the objective of defining further potential drill targets.
Figure 5: Mt Sholl Project with the results of Raiden’s lithium infill soil sampling program, in relation
to GreenTech Metals Ltd.’s Osbourne JV results12,13
Page 7 of 16
ASX RELEASE | 15 April 2024
Arrow Project
The Company has not undertaken any further field activities on the project during the
reporting period. Activities included further planning for the upcoming field season in
relation to follow up on the pegmatites which have been defined to date 14. In parallel,
management have undertaken a review of the gold results on the project to determine
how these areas of interest may relate to the future lithium exploration activities.
Other Australian Projects
Management continued to engage with potential partners regarding the divestment and
partnerships regarding non-core assets in Australia.
Page 8 of 16
ASX RELEASE | 15 April 2024
Exploration Activities in Bulgaria
Vuzel (Au/Ag)
During the reporting period no field activities were undertaken on the project. The
Company, through its 51% owned Bulgarian subsidiary, Vuzel Minerals Ltd. Management
continued with planning for a drill campaign on the project, which will be undertaken in
the second quarter of 2024, with the objective to follow up on the high grade targets
defined on the project to date.
Kalabak (Cu/Au)
Due to the demonstrated lack of obvious prospectivity on the project, management made
the decision to terminate the exploration agreement with the Ministry of Energy of
Bulgaria and have relinquished the project. The Company does not have any further
obligation in regard to this project.
Zlatusha (Cu/Au)
Throughout the reporting period, further target refining and generative work was been
undertaken on the project by Velocity Minerals, as per the option/earn-in agreement, as
announced by the Company on the 24th of January 2023 15. Velocity Minerals, as the
operator of the project are also making plans to undertake further community
consultations with the communities within the exploration license, prior to undertaking
the planned drilling program on the license.
BG1 project (Cu/Au)
No activities were undertaken on the project during the reporting period.
Exploration Activities in Serbia
Donje Nevlje (Cu/Au)
No activities were undertaken on the project during the reporting period.
Page 9 of 16
ASX RELEASE | 15 April 2024
Corporate
Performance Rights
As at the 31 March 2024, the Company held 73,000,000 Performance Rights (issued in
2021) on issue with various vesting conditions to Directors (including former Director
Martin Pawlitschek) and 5,000,0000 Performance Rights (issued in 2023) on issue to other
KMP with various vesting conditions.
During the quarter the Board resolved that 54,750,000 Performance Rights had vested on
satisfaction of the relevant milestone being met.
Security
Class
Number
Expiry
Date
Milestone
Performance
21,900,000
6 October
The Company achieving a VWAP of at least $0.055 over a period of 20
consecutive trading days (on which the entity’s shares have actually
traded) on or before the Expiry Date.
Rights
2024
Tranche 1
Performance
7,300,000
Rights
6 October
2024
Tranche 2
Performance
25,550,000
Rights
Tranche 3
6 October
2024
Achieving a minimum of 7,500 metre drilling, in aggregate (by the
Company or its joint venture partners), across any of the projects the
Company has an interest (being the Company’s existing projects as at
the date of issue of the Performance Rights and listed in Schedule 3)
on or before the Expiry Date.
The Company achieving:
a)
a VWAP of at least $0.075 over a period of 20 consecutive
trading days (on which the entity’s shares have actually
traded) on or before Expiry Date; or
b) a market capitalisation of A$100 million over a period of 20
consecutive trading days (on which the entity’s shares have
actually traded) on or before the Expiry Date
Further information regarding the terms and conditions surrounding the Performance
Rights can be found in the Notice of Meeting as announced to the ASX on 7 September
2021.
Listed Options
40,965,208 listed options with an exercise price of $0.04 lapsed and were cancelled.
Page 10 of 16
ASX RELEASE | 15 April 2024
Summary of Expenditure
Of the total expenditure of the Company during the Quarter, $705k of the Company’s
expenditure was on activities related to the exploration of the current projects as detailed
in the Cashflow Report (5B) appended to this report. The Company did not incur any
expenditure related to mining, production and development activities during the Quarter.
In accordance with ASX Listing Rule 5.3.5 payments totalling approximately $119k were
made to related parties of the Company, being Non-Executive, Managing Director fees
and accounting and company secretarial fees (section 6.1 of the accompanying 5B).
Tenement Table: ASX Listing Rule 5.3.3
Mining tenement interests held at the end of the quarter and their location:
Tenement reference
Location
Donje Nevlje 310-021547/2015-02
Zapadni Majdanpek
310-02-1096/201602
Zlatusha (Bulgaria) –
Licence No. 486
BG1 (Bulgaria) –
Permit No. 527
Mt Sholl (E47/4309)
Serbia
Western Australia
Direct
Granted
100%
Mt Sholl (E47/3468)
Western Australia
Direct
Granted
100%
Mt Sholl (P47/2024)
Western Australia
Direct
Granted
100%
Mt Sholl (E47/3181)
Western Australia
Direct
100%
Mt Sholl (E47/3339)
Western Australia
Direct
100%
Mt Sholl (P47/1762)
Western Australia
Direct
100%
Mt Sholl (P47/1787)
Western Australia
Direct
100%
Mt Sholl (P47/1788)
Western Australia
Direct
Mt Sholl (P47/1789)
Western Australia
Direct
Mt Sholl (P47/1790)
Western Australia
Direct
Mt Sholl (P47/1791)
Western Australia
Direct
Mt Sholl (P47/1792)
Western Australia
Direct
100%
Mt Sholl (P47/1793)
Western Australia
Direct
100%
Mt Sholl (P47/1794)
Western Australia
Direct
100%
Mt Sholl (P47/1795)
Western Australia
Direct
100%
Serbia
Bulgaria
Bulgaria
Nature
Status
Interest
Direct
Granted
100%
Direct
Granted
100%
Direct
Granted
100%
Direct
Pending
100%
Granted – subject to approval of
the Welcome Exploration Pty Ltd
transaction and the transfer of the
remaining 20% interest to the
Company
100%
100%
100%
100%
Page 11 of 16
ASX RELEASE | 15 April 2024
Tenement reference
Location
Nature
Status
Interest
Yandicoogina
(M45/115)
Yandicoogina
(M45/987)
Arrow (E47/3476)
Western Australia
Direct
Granted
100%
Western Australia
Direct
Granted
100%
Western Australia
Direct
Granted
100%
Arrow (E47/3478)
Western Australia
Direct
100%
Pyramid (E47/4300)
Western Australia
Direct
Granted – currently subject to
Forfeiture after a recent Wardens
Court decision rejecting Raiden’s
Expenditure Exemption application.
Raiden are currently following due
process to resolve this issue
Granted
Welcome (E47/3849)
Western Australia
Direct
Granted
80%
Welcome (E47/4061)
Western Australia
Direct
Granted
80%
Welcome (E47/4063
Western Australia
Direct
Granted
80%
100%
Mining tenement interests relinquished during the quarter and their location:
Tenement reference
Location
Nature
Status
Interest
Yandicoogina (E45/3571)
Western Australia
Direct
Surrendered
100%
Yandicoogina (E45/3474)
Western Australia
Direct
100%
Tabba Tabba (E45/6182)
Western Australia
Direct
Kalabak (Licence No. 405)
Bulgaria
Direct
Surrendered
Application
withdrawn
Relinquished
100%
100%
Mining tenement interests acquired during the quarter and their location:
Tenement reference
Location
Nature
Status
Interest
Mt Sholl (E47/3181)
Western Australia
Direct
20%
Mt Sholl (E47/3339)
Western Australia
Direct
20%
Mt Sholl (P47/1762)
Western Australia
Direct
20%
Mt Sholl (P47/1787)
Western Australia
Direct
Mt Sholl (P47/1788)
Western Australia
Direct
Mt Sholl (P47/1789)
Western Australia
Direct
Mt Sholl (P47/1790)
Western Australia
Direct
Mt Sholl (P47/1791)
Western Australia
Direct
Mt Sholl (P47/1792)
Western Australia
Direct
Mt Sholl (P47/1793)
Western Australia
Direct
20%
Mt Sholl (P47/1794)
Western Australia
Direct
20%
Mt Sholl (P47/1795)
Western Australia
Direct
20%
Granted – subject to
approval of the
Welcome Exploration
Pty Ltd transaction and
the transfer of the
remaining 20% interest
to the Companya
20%
20%
20%
20%
20%
20%
Page 12 of 16
ASX RELEASE | 15 April 2024
a The Company entered into an arrangement to acquire the remaining 20% interest in the Mt Sholl tenements from
Welcome Exploration Pty Ltd on the 12th December 2023 to increase Raiden’s beneficial interest in the tenements to
100%.
Mining tenement interests under application during the quarter and their location:
Tenement reference
Majdanpek Pojas - 310-02-1999
/2020-02
Tabba Tabba (E45/6701)
Location
Nature
Status
Interest
Serbia
Direct
Application - pending
100%
Western Australia
Direct
Application - pending
100%
Pyramid (E47/4307)
Welcome (E47/4062)
Western Australia
Western Australia
Direct
Direct
Application - pending
Application - pending
100%
80%
Welcome (P47/2028)
Western Australia
Direct
Application - pending
80%
Andover (E47/4603)
Western Australia
Direct
Application - pending
100%
Andover (E47/5038)
Western Australia
Direct
Application - pending
100%
Beneficial percentage interests held in farm-in or farm-out agreements at the end
of the quarter:
Tenement reference
Vuzela (Bulgaria) – Licence No. 522
Location
Nature
Status
Interest
Bulgaria
Joint Venture
Granted
51%
a The Company has an agreement to earn-in up to 90% position within the project. At the end of the quarter the
Company held 51% interest in Vuzel Minerals EOOD, which holds the Vuzel licence.
This ASX announcement has been authorised for release by the Board of Raiden Resources
Limited.
FOR FURTHER INFORMATION PLEASE CONTACT
DUSKO LJUBOJEVIC
Managing Director
RAIDEN RESOURCES LIMITED
info@raidenresources.com.au
www.raidenresources.com.au
Page 13 of 16
ASX RELEASE | 15 April 2024
ASX Announcements referenced to directly, or in the commentary of, this quarterly activities release
ASX:RDN 06 March 2024 Heritage survey secured for Andover South Project
1
ASX:RDN 13 March 2024 Heritage survey secured for Andover North Project
2
ASX:RDN 22 March 2024 New Ni & Cu prospects defined at Mt Sholl Amendment
3
ASX:RDN 21 February 2024 IP Survey indicates significant Ni-Cu-PGE upside potential
4
ASX:RDN 22 March 2024 Infill sampling confirms high priority lithium anomalies
5
ASX:RDN 09 November 2023 Exceptional lithium results & additional spodumene XRD confirmation at
Andover South Project
6
ASX:RDN 19 JUN 2023 Roebourne Lithium Project Review Confirms Prospectivity
7
ASX:AZS 13 February 2024 More Very Impressive Lithium Intersections from Andover
8
ASX:RDN 21 February 2024 IP Survey at B2 Ni-Cu-PGE deposit indicates significant upside potential at Mt
Sholl Project
9
ASX:RDN 13 December 2023 Raiden enters into Memorandum of Understanding over Mt Sholl Ni-Cu-PGE
Project
10
ASX:RDN 03 April 2023 Maiden Mineral Resource Estimate & JORC Exploration Target
11
ASX:RDN 05 December 2023 Multiple lithium soil anomalies defined at Mt Sholl project
12
ASX:GRE 29 November 2023 Maiden diamond Hole completed Osborne Joint Venture
13
ASX:RDN 30 October 2023 Pegmatites and Visual Spodumene Mineralisation mapped at Arrow Lithium
Project
14
ASX:RDN 24 January 2023 Sale of up to 75% in Zlatusha Project through minimum earn-in requirements
& c$1m Cash/Script
15
Competent Person's and Compliance Statement
The information in the referenced announcement 3-7, 9-12 and 14-15 footnoted above that relate to
Exploration Results have previously been released to the ASX. The Company confirms that it is not aware of
any information or data that materially affects the information included in the market announcements, and
that all material assumptions and technical parameters underpinning the announcements continue to apply.
The Company confirms that the form and context in which the Competent Person’s findings are presented
have not been materially modified from the original market announcements.
Page 14 of 16
ASX RELEASE | 15 April 2024
Mineral Resources
The Company confirms it is not aware of any new information or data that materially affects the information
included in the announcement released on 3 April 2023 and all material assumptions and technical
parameters underpinning the estimate continue to apply and have not materially changed when referring
to its resource announcement. The Company confirms that the form and context in which the Competent
Person’s findings are presented have not been materially modified from the original market announcement.
Mineral Resources Estimate
The Mineral Resource statement as reported on the 3 April 2023 is as follows:
Mt Sholl Mineral Resource Estimate by classification reported above a 0.35% Ni_Eq cut-off for open pit
resources and at 0.5% Ni_Eq for underground resources
Tonnes
Mt
Ni
%
Cu
%
Co
ppm
3E1
g/t
Ni Metal
kt
Cu Metal
kt
3E
(Pd, Pt, Au)
oz
Indicated
10.5
0.39
0.45
134
0.32
41.0
47.3
108,031
Inferred
9.8
0.29
0.32
78
0.32
28.4
31.3
100,715
Total
20.3
0.34
0.39
107
0.32
69.34
78.6
208,745
3.1
0.48
0.47
57
0.25
14.9
14.6
24,898
Classification
Open Pit
Underground
Inferred
Notes:
•
•
•
•
•
Mineral Resources are reported in accordance with the Australasian Code for Reporting of Exploration Results, Mineral
Resources and Ore Reserves (The Joint Ore Reserves Committee Code –JORC 2012 Edition).
Data is reported to significant figures and differences may occur due to rounding.
Mineral Resources have been reported above a cut-off grade of 0.35 % Nickel equivalent for open pit resources and above
0.5% Nickel equivalent for underground resources.
Bulk densities in the Basal unit are 3.06 and in Zone2 are 2.91. These figures represent averages of the values collected in
the respective domains from the 2022 drill program.
The Ni_Eq calculation represents total metal value for each metal summed and expressed in equivalent nickel grade and
tonnes. Commodity prices assumed in the calculation are noted below as is the formula used to calculate Ni_Eq.
Page 15 of 16
ASX RELEASE | 15 April 2024
Disclaimer:
Forward-looking statements are statements that are not historical facts. Words such as “expect(s)”, “feel(s)”,
“believe(s)”, “will”, “may”, “anticipate(s)”, “potential(s)”and similar expressions are intended to identify
forward-looking statements. These statements include, but are not limited to statements regarding future
production, resources or reserves and exploration results. All of such statements are subject to certain risks
and uncertainties, many of which are difficult to predict and generally beyond the control of the Company,
that could cause actual results to differ materially from those expressed in, or implied or projected by, the
forward-looking information and statements. These risks and uncertainties include, but are not limited to:
(i) those relating to the interpretation of drill results, the geology, grade and continuity of mineral deposits
and conclusions of economic evaluations, (ii) risks relating to possible variations in reserves, grade, planned
mining dilution and ore loss, or recovery rates and changes in project parameters as plans continue to be
refined, (iii) the potential for delays in exploration or development activities or the completion of feasibility
studies, (iv) risks related to commodity price and foreign exchange rate fluctuations, (v) risks related to
failure to obtain adequate financing on a timely basis and on acceptable terms or delays in obtaining
governmental approvals or in the completion of development or construction activities, and (vi) other risks
and uncertainties related to the Company’s prospects, properties and business strategy. Investors are
cautioned not to place undue reliance on these forward-looking statements that speak only as of the date
hereof, and the Company does not undertake any obligation to revise and disseminate forward-looking
statements to reflect events or circumstances after the date hereof, or to reflect the occurrence of or nonoccurrence of any events.
About Raiden Resources
Raiden Resources Limited (ASX:RDN / DAX:YM4) is a dual listed transition energy-metal—gold exploration
Company focused on exploring and developing the Andover Lithium project, the Mt Sholl Lithium project
and the Mt Sholl Ni-Cu-Co-PGE deposit in the Pilbara region of Western Australia. The Company also has a
significant portfolio of exploration projects in WA, including the Arrow Lithium and Gold projects, which
gold project is located 30km along strike from the Hemi discovery. In the emerging and prolific Western
Tethyan metallogenic belt in Eastern Europe, the Company has established a significant exploration
footprint in Serbia and Bulgaria. The Directors believe that the Company is well positioned to unlock value
from this exploration portfolio and deliver a significant mineral discovery.
Page 16 of 16
Rule 5.5
Appendix 5B
Mining exploration entity or oil and gas exploration entity
quarterly cash flow report
Name of entity:
RAIDEN RESOURCES LIMITED (RDN)
ABN
Quarter ended (“current quarter”)
68 009 161 522
31 March 2024
Current quarter
$A’000
Year to date
(9 months)
$A’000
(705)
(2,413)
(b) development
-
-
(c) production
-
-
(d) staff and board remuneration
(114)
(382)
(e) administration and corporate costs
(98)
(805)
-
-
36
78
Consolidated statement of cash flows
1.0
Cash flows from operating activities
1.1
Receipts from customers
1.2
Payments for:
(a) exploration & evaluation
1.3
Dividends received
1.4
Interest and other items of a similar nature received
1.5
Interest and other costs of finance paid
-
-
1.6
Income taxes paid
-
-
1.7
Government grants and tax incentives
-
-
1.8
Other - Loan Repayment from Balkan Mineral
Development
-
-
1.8
Other - Konstantin and bank guarantees
95
144
1.8
Other - contributions from Velocity
245
762
1.9
Net cash from / (used in) operating activities
(541)
(2,616)
2.0
Cash flows from investing activities
2.1
Payments to acquire:
-
-
(10)
(460)
(c) property, plant and equipment
-
-
(d) exploration if capitalised
-
-
(e) investments
-
-
(f)
-
-
(a) entities
(b) tenements
other non-current assets
ASX Listing Rules Appendix 5B (17/07/20)
+ See chapter 19 of the ASX Listing Rules for defined terms.
Page 1
Appendix 5B
Mining exploration entity or oil and gas exploration entity quarterly cash flow report
Current quarter
$A’000
Year to date
(9 months)
$A’000
(a) entities
-
-
(b) tenements
-
11
(c) property, plant and equipment
-
-
(d) investments
-
-
(e) other non-current assets
-
-
2.3
Cash flows from loans to other entities
-
-
2.4
Dividends received
-
-
2.5
Other
-
-
2.6
Net cash from / (used in) investing activities
(10)
(449)
3.0
Cash flows from financing activities
3.1
Proceeds from issues of equity securities (excluding
convertible debt securities)
-
6,916
3.2
Proceeds from issue of convertible notes
-
3.3
Proceeds from exercise of share options
11
2,888
3.4
Transaction costs related to issues of shares,
convertible notes or options
-
(275)
3.5
Proceeds from borrowings
-
-
3.6
Repayment of borrowings
-
-
3.7
Transaction costs related to loans and borrowings
-
-
3.8
Dividends paid
-
-
3.9
Other (provide details if material)
-
-
3.1
0
Net cash from / (used in) financing activities
11
9,529
4.0
Net increase / (decrease) in cash and cash
equivalents for the period
4.1
Cash at beginning of quarter/year to date
7,714
738
4.2
Net cash from / (used in) operating activities (item 1.9
above)
(541)
(2,616)
4.3
Net cash from / (used in) investing activities (item 2.6
above)
(10)
(449)
4.4
Net cash from / (used in) financing activities
(item 3.10 above)
11
9,529
4.5
Effect of movement in exchange rates on cash held
14
(14)
4.6
Cash and cash equivalents at end of period
7,188
7,188
Consolidated statement of cash flows
2.2
Proceeds from the disposal of:
*Refer additional information provided at 8.2.2 below
ASX Listing Rules Appendix 5B (17/07/20)
+ See chapter 19 of the ASX Listing Rules for defined terms.
Page 2
Appendix 5B
Mining exploration entity or oil and gas exploration entity quarterly cash flow report
5.0
Reconciliation of cash and cash equivalents
at the end of the quarter (as shown in the
consolidated statement of cash flows) to the related
items in the accounts
5.1
Bank balances
5.2
Current quarter
$A’000
Previous
quarter
$A’000
7,188
7,714
Call deposits
-
-
5.3
Bank overdrafts
-
-
5.4
Other (provide details)
-
-
5.5
Cash and cash equivalents at end of quarter
(should equal item 4.6 above)
7,188
7,714
*Refer additional information provided at 8.2.2 below
6.0
Payments to related parties of the entity and
their associates
Current quarter
$A'000
6.1
Aggregate amount of payments to the parties in
item 1.2
6.2
Aggregate amount of cash flow from loans to these
parties included in item 2.3
-
6.3
Include below any explanation necessary to
understand the transactions included in items 6.1 and
6.2
-
6.4
Payment for executive salary and non executive
director fees and payments to Onyx Corporate Pty
Ltd for accounting and company secretarial fees.
119
119
Note: if any amounts are shown in items 6.1 or 6.2, your quarterly activity report must include a description of, and an
explanation for, such payments.
Payment of executive salary and non-executive director fees ($90,999), and payments to related parties for accounting and
company secretarial services ($27,750).
ASX Listing Rules Appendix 5B (17/07/20)
+ See chapter 19 of the ASX Listing Rule
Share your feedback