SILVER ANOMALY PERMIT PROGRESSING & IP
DATA PROCESSING AT VUZEL
QUICK STATS
HIGHLIGHTS
ASX Code: RDN
•
Raiden has applied for a permit to drill the nearby Skarn Silver
Anomaly situated on the Vuzel Exploration project.
•
In addition, a 10 line-km Induced Polarisation (“IP”) geophysical
survey has been completed to define the trends and full extent of
the previously intercepted gold feeder structure1, as well as to assist
in identifying other potential feeder structures within the
targeted area. The IP work undertaken includes survey coverage of
the Silver Skarn Anomaly.
•
•
•
•
The IP survey data is currently being processed, the results of which
will assist in targeting high-grade gold zones within Vuzel and to
further define drill targets over the silver skarn anomaly.
To date, approximately 3,450m of drilling has been completed,
with all samples sent to the laboratory for analysis. Final results are
anticipated by the end of the month.
To maximise the value of the program, the remaining ~550m of
drilling, along with any additional planned drilling, has been paused
to allow for the completion of permitting of the skarn silver anomaly
and the processing of the IP results.
DAX Code: YM4
BOARD &
MANAGEMENT
Non-Executive Chairman
Mr Michael Davy
Managing Director
Mr Dusko Ljubojevic
Non-Executive Director
& Company Secretary
Ms Kyla Garic
Chief Operating Officer
Mr Sean Halpin
ASSET PORTFOLIO
AUSTRALIA
Li, Au, Cu, Ni & PGE
BULGARIA
Cu, Au & Ag
Raiden views Vuzel as a strategic asset within the Company’s portfolio and believes it may host
a substantial near-surface gold system, characterised by both widespread mineralisation and
potentially multiple high-grade feeder zones.
• Engage directly with us by commenting on our latest announcements via InvestorHub. You
can view and comment on this announcement here.
Raiden Resources Limited (ASX: RDN) (“Raiden” or “the Company”) is pleased to provide an
update on its ongoing exploration activities at the Vuzel Gold Project, including progress on
A: Downhole width is not equivalent to true thickness. Structural
measurement and analysis of drill core is ongoing to establish the true
orientation of the mineralisation.
P 08 6158 9990
Suite 7, 63 Shepperton Road, Victoria Park, WA 6100
ABN 68 009 161 522
Page 1 of 7
ASX RELEASE | 14th August 2025
permitting for the nearby silver anomaly and the processing of recently completed IP survey results,
which will guide the next phase of drilling.
Mr Dusko Ljubojevic, Managing Director of Raiden commented:
“The completion of the IP survey and progress on permitting for the nearby silver anomaly represent
important milestones in advancing our work at Vuzel. The IP geophysical results will give us a clearer
understanding of the structural trends across the target area, which we plan to integrate with our
existing drilling data. This will enable us to potentially target high-grade zones, while maintaining our
ongoing commitment to prioritise high-impact and cost-effective exploration.
While the remaining 550 meters of drilling is temporarily paused to accommodate permitting and data
processing, our technical team is using this time to refine the geological model and plan the next phase
of drilling. With 3,450 meters of drilling completed to date and with further targets to be tested, we
remain confident in the potential scale and significance of the Vuzel system and look forward to
resuming drilling as soon as possible.”
SKARN SILVER ANOMALY – PERMITTING UNDERWAY
Raiden has applied for access permits , with the plan to drill test the previously identified Skarn Silver
Anomaly at the Vuzel Exploration Permit, illustrated in Figure 1 below.
Page 2 of 7
ASX RELEASE | 14th August 2025
Figure 1: Vuzel Exploration permit, structures, exploration targets, including the nearby Skarn Ag Anomaly
and drilling (as of 1st July 2025)1.
The Skarn Silver Anomaly was originally defined as a coherent 500 m x 300 m silver-in-soil footprint
with a classic pathfinder suite (Pb-Zn-Cu-As-Sb-Ba)2. At this time it is not clear whether the silver
mineralisation is a separate hydrothermal event from the nearby gold targets.
The best historical intervals include rock-chip/channel silver sampling intervals (e.g. 83 m @ 43.8 g/t
Ag) and a historical diamond hole (KKDD015), intersecting 9 m @ 63.7 g/t Ag from 0 metres, which
suggests continuity of mineralisation along a shallow-dipping contact2. These results define the Skarn
Silver Anomaly as one of the priority targets on the project, in conjunction with the high-grade feeder
zones.
More recent field checks by Raiden in 20212 replicated and refined the silver footprint on outcrop,
returning channel results of 10 m @ 49 g/t Ag, 6 m @ 38 g/t Ag, and 3 m @ 34 g/t Ag from pervasively
silicified limestone exposures.
Geologically, the Skarn Silver Anomaly sits along a shallow-dipping limestone/tuff contact with
pervasive silicification. An adjacent linear gravity feature is interpreted as a major regional structure,
Page 3 of 7
ASX RELEASE | 14th August 2025
providing a plausible fluid pathway and structural control on mineralisation. The combination of
reactive carbonate stratigraphy, silicification, and the pathfinder suite provides a robust framework
for vectoring towards thicker or higher-grade shoots along the contact.
Subject to receipt of the required permits (currently pending), Raiden intends to recommence drilling
at the Skarn Silver Anomaly. The programme will be guided by integrating the historical soil, channel
and drill data, with the newly acquired IP survey (now being processed) to prioritise well informed
and high-impact targets along the contact zone.
10 LINE-KM IP SURVEY
Raiden recently completed a 10 line-km IP survey across the Vuzel Project area. The survey data is
currently being processed, with results expected to provide a clearer understanding of the structural
trends and potential feeder zones along the target area. Raiden considers this work an important
step in ensuring the cost-effectiveness of the ongoing campaign and in focusing future drilling on
the most prospective, high-impact targets. The integration of existing drilling data will greatly assist
in the interpretation of the IP results, allowing the Company to refine its geological model and define
high-priority drill targets for the remaining phase of the Vuzel campaign.
DRILLING & NEXT STEPS
To date, 3,450m of drilling has been completed at Vuzel, with all samples sent for laboratory analysis.
The remaining 550m of drilling of the originally budgeted 4,000m second phase drill campaign has
been paused, pending the processing of IP results and permitting of the Skarn Silver Anomaly.
STRATEGIC VALUE OF VUZEL
The type of geology and setting at Vuzel is similar to that of the epithermal low sulphidation Ada
Tepe deposit, which is currently being mined by Dundee Precious Metals only 30km south-east of
Vuzel (see Figure 2) (TSX: DPM). In addition, Vuzel is located <20km from Gorubso-Kardzhali A.D. (a
Bulgarian Mining company) gold processing facility3, whom is also a 30% partner of TSX-V Velocity
Minerals whose Bulgarian portfolio, including the Rozino deposit (573Koz@0.8g/t Au) was recently
subject of a US$59M4 acquisition by Türker Mining, a subsidiary of the Turkish conglomerate Türkerler
Holding.
Page 4 of 7
ASX RELEASE | 14th August 2025
Figure 3 - Location of Vuzel project in Southern Bulgaria in relation to other operating and historical
mine/prospects.
This ASX announcement has been authorised for release by the Board of Raiden Resources
Limited.
We value your feedback and questions.
Engage directly with us by commenting on our latest announcements via InvestorHub.
You can view and comment on this announcement here.
Page 5 of 7
ASX RELEASE | 14th August 2025
FOR FURTHER INFORMATION PLEASE CONTACT
DUSKO LJUBOJEVIC
Managing Director
RAIDEN RESOURCES LIMITED
dusko@raidenresources.com.au
www.raidenresources.com.au
ASX Announcements referenced in this release
1
ASX:RDN 1 July 2025 “High Grade Feeder Zone Intersected at Vuzel Gold Project”
2
ASX:RDN 10 May 2021 “Significant Gold and Silver Results from surface sampling at Vuzel Project”
Other releases and material referenced in this release
3
https://velocityminerals.com/projects/overview/
4
TSXV: VLC 28 February 2025 Velocity Enters into Definitive Agreement to Sell All Bulgarian Assets
Competent Person's and Compliance Statement
The information in the referenced announcements 1-2 footnoted above that relate to Exploration Results have previously
been released on the ASX. The Company confirms that it is not aware of any information or data that materially affects the
information included in the market announcements, and that all material assumptions and technical parameters
underpinning the announcements continue to apply. The Company confirms that the form and context in which the
Competent Person’s findings are presented have not been materially modified from the original market announcements.
Disclaimer:
Forward-looking statements are statements that are not historical facts. Words such as “expect(s)”, “feel(s)”, “believe(s)”,
“will”, “may”, “anticipate(s)”, “potential(s)”and similar expressions are intended to identify forward-looking statements.
These statements include, but are not limited to statements regarding future production, resources or reserves and
exploration results. All of such statements are subject to certain risks and uncertainties, many of which are difficult to
predict and generally beyond the control of the Company, that could cause actual results to differ materially from those
expressed in, or implied or projected by, the forward-looking information and statements. These risks and uncertainties
include, but are not limited to: (i) those relating to the interpretation of drill results, the geology, grade and continuity of
mineral deposits and conclusions of economic evaluations, (ii) risks relating to possible variations in reserves, grade,
planned mining dilution and ore loss, or recovery rates and changes in project parameters as plans continue to be refined,
(iii) the potential for delays in exploration or development activities or the completion of feasibility studies, (iv) risks
related to commodity price and foreign exchange rate fluctuations, (v) risks related to failure to obtain adequate financing
on a timely basis and on acceptable terms or delays in obtaining governmental approvals or in the completion of
development or construction activities, and (vi) other risks and uncertainties related to the Company’s prospects,
properties and business strategy. Investors are cautioned not to place undue reliance on these forward-looking
statements that speak only as of the date hereof, and the Company does not undertake any obligation to revise and
disseminate forward-looking statements to reflect events or circumstances after the date hereof, or to reflect the
occurrence of or non-occurrence of any events
About Raiden Resources
Page 6 of 7
ASX RELEASE | 14th August 2025
Raiden Resources Limited (ASX:RDN / DAX:YM4) is a dual listed base metal & gold exploration Company focused on
identifying and discovering significant and economically attractive mineral deposits. Driven by a passion for unlocking
discoveries that create shareholder value and the support of a strong corporate treasury, Raiden is committed to achieving
exploration success.
The Company’s portfolio of projects covers Western Australia and Eastern Europe. In the Pilbara region of Western
Australia, the Company has 100% interest in each of the Andover South lithium project, the advanced Mt Sholl nickelcopper-cobalt-PGE and the Arrow gold project. In addition, the Company holds the rights to multiple projects in the
emerging and prolific Western Tethyan metallogenic belt in Eastern Europe, where it has established a significant
exploration footprint in Bulgaria.
Page 7 of 7
Share your feedback
Discover